The City of De Pere retained Robert E. Lee & Associates to prepare plans and specifications for the reconditioning of the 9th street 250,000-gallon, multi-legged elevated storage tank. The project consisted of blasting with full containment and repainting the interior and exterior of the elevated storage tank. A new PAX mixer system was installed for tank mixing and to prevent ice build-up during the cold winter months. The perimeter handrail around the exterior of the bowl was raised to meet code requirements. Miscellaneous hatches and vents were replaced and enlarged.
Project Location

City of De Pere, WI

Client

City of De Pere

Category
Services Used

Civil Engineering, Construction Services, Municipal Engineering, Water Systems