Project Highlights
The Village of Whitelaw required a chemical feed system for phosphorus removal to meet stricter effluent limits from the State of Wisconsin before the operational deadline set by the Village’s WPDES permit.
- New chemical feet building
- Two 2,500-gallon chemical storage tanks
- Chemical transfer pump
- Duplex chemical feed skid
Project Details
REL effectively coordinated with the Wisconsin Department of Natural Resources (DNR) throughout the planning, design, and installation phases of the chemical feed system aimed at phosphorus removal, ensuring compliance with the Water Pollution Discharge Elimination System (WPDES) operational permit deadline.
Stakeholder Coordination
During the Facility Plan stage of the project, a public hearing was organized to engage the community and provide a comprehensive overview of the proposed improvements, particularly the installation of a chemical feed system for phosphorus removal. The meeting aimed to outline the necessity of the project in response to stricter state effluent limits, highlighting the environmental and regulatory implications of phosphorus discharge on local water bodies. This stakeholder engagement ensured that the public was informed and invested in the project’s objectives, ultimately aiding in its support and successful implementation.