Greenleaf MDV Chemical Addition Project

2025-05-21T19:59:54+00:00

Project Highlights

The Wrightstown Sanitary District No. 1 needed to implement a chemical feed system for phosphorus removal in order to comply with the new, stricter effluent limits mandated by the State of Wisconsin, all while adhering to the operational deadline established by the Village’s Water Pollution Discharge Elimination System (WPDES) permit.

  • New chemical feet building
  • Two 2,500-gallon chemical storage tanks
  • Chemical transfer pump
  • Duplex chemical feed skid

Project Details

REL effectively coordinated with the Wisconsin Department of Natural Resources (DNR) throughout the planning, design, and installation phases of the chemical feed system aimed at phosphorus removal, ensuring compliance with the WPDES operational permit deadline.

Stakeholder Coordination

During the Facility Plan stage of the project, a public hearing was organized to engage the community and provide a comprehensive overview of the proposed improvements, particularly the installation of a chemical feed system for phosphorus removal. The meeting aimed to outline the necessity of the project in response to stricter state effluent limits, highlighting the environmental and regulatory implications of phosphorus discharge on local water bodies. This stakeholder engagement ensured that the public was informed and invested in the project’s objectives, ultimately aiding in its support and successful implementation.

Project Location

Greenleaf, WI

Client

Village of Greenleaf

Category
Services Provided

Whitelaw Chemical Addition Project

2025-05-21T17:03:16+00:00

Project Highlights

The Village of Whitelaw required a chemical feed system for phosphorus removal to meet stricter effluent limits from the State of Wisconsin before the operational deadline set by the Village’s WPDES permit.

  • New chemical feet building
  • Two 2,500-gallon chemical storage tanks
  • Chemical transfer pump
  • Duplex chemical feed skid

Project Details

REL effectively coordinated with the Wisconsin Department of Natural Resources (DNR) throughout the planning, design, and installation phases of the chemical feed system aimed at phosphorus removal, ensuring compliance with the Water Pollution Discharge Elimination System (WPDES) operational permit deadline.

Stakeholder Coordination

During the Facility Plan stage of the project, a public hearing was organized to engage the community and provide a comprehensive overview of the proposed improvements, particularly the installation of a chemical feed system for phosphorus removal. The meeting aimed to outline the necessity of the project in response to stricter state effluent limits, highlighting the environmental and regulatory implications of phosphorus discharge on local water bodies. This stakeholder engagement ensured that the public was informed and invested in the project’s objectives, ultimately aiding in its support and successful implementation.

Project Location

Whitelaw, WI

Client

Village of Whitelaw

Category
Services Provided